to split the component will not help, the need is to distribute the finish goods through the month on weekly buckets, once the finish goods are on weekly bucket, i don't care if the all the components demand is at the beginning of the period.
i need a macro or heuristic to split the quantity, see the example below, the planner has monthly view in which he had entered 55,000 PC for month 10.2014, before i transfer this quantity to the ECC i need to split it to weekly buckets:
simple MRP run will not work, because the planner may plan to produce more than the total demand.